this blog is a record of the house that I helped to build along with my class during the Carpentry pretrade course I did at SIT chch

Sunday 12 August 2012

crack injection

recently I have been working on a commercial tilt slab building doing crack injection to fix damage from the Feb 2011 quakes here in Christchurch.
This process involves locating the cracks, grinding off the paint to expose them, any cracks that are over 0.2mm in width then have 30mm deep holes drilled at 120mm centres  to allow injection, a sealant spread over the the total length of the crack then plastic injection nipples are glued on.
Once the glue has set a epoxy resin is injected into the crack through the nipples.
once the resin has set the nipples are removed and the sealant is ground off and the crack plastered over to allow for repainting.
this is a very time consuming process that can be quite tedious but I quite enjoyed it.

the building with cracks exposed
blown out panel that will need replacing
grinding and measuring crack lengths
crack with injection holes drilled
cracks with sealant and nipples glued on
same again using a different sealant

holes with nipples removed showing resin, sealant has been scrapped off

Thursday 26 July 2012

House renovation

One of the jobs that i have recently been involved with is a house reno, this involved removing a fireplace and existing wall, opening the floor and installing an extra load bearing pile.
then the wall was reinstalled with a door where the fire place was, the walls were brought up to current bracing standards then relined them with bracing GiB.
we also removed a window and replaced it with a new aluminum unit.
the brick fire place
Me taking it apart
the wall behind the fireplace to be removed
opening up the floor
wall lining removed and floor open
fireplace exposed
new pile in
new steel beam in to replace wall
Lath and plaster walls
fitting new bracing GiB
new wall with new door 
GiB on
removing plaster around window
window removed
window rough opening to be reframed
new window in.

Monday 16 July 2012

recladding an external wall

For the last week I have mainly been removing the bricks from the outside of the house that I am working on but today I got to re clad the outside of of room.
This involved removing the building paper, measuring for the new Eco-ply cladding, fitting a new trimming stud to allow for the fixing of the two sheets, fitting extra bracing using Handi-brackets, I put in 4 of these.
I then cut the two sheets of ply fitted them and nailed them off to the bracing pattern of 150mm centers, tomorrow I will tape seal the joints and re install flashing's around the window.
removing the building paper
measuring up for the ply
fixing in the extra trimmer stud
drilling the holes for the coach bolts
Handi-brackets in place
nailing off the ply
and it's done
me with my work

Saturday 7 July 2012

replaceing temp cladding with bracing ply

 This week we started to remove the block work from the north side of the house down to the height of the first floor so we can check and update the bracing.
The bricks on the upper story have a cavity but the lower story blocks have been filled to form a solid foundation for the concrete floor.
On Friday myself and a work mate took down the temp cladding that was put up after the feb2011 quake and replaced it with Eco ply bracing.
We started at the top of the North Gable wall down to the height of the top windows, next week we will finish removing the bricks, paper and existing bracing ply lower down and do the same there.

north end of the house with temp cladding at the top where the bricks fell off in the Feb 2011 Qauke
Typical quake damage
Ali taking down the bricks
Me taking down some bricks
Brick cavity with paper behind, note this cavity no longer meets the current standard of 50mm so will need to be modified when the bricks are put back.
solid filled lower story blocks
Ali removing the temp cladding
With the temp ply removed we can see that the stell lintel above the windows that was only mortared into the bricks is now just sitting there not supporting anything
cutting and fitting new blocking and dwangs for the eco ply to fix to
Me nailing in blocking to allow fixing for the eco ply
and some more
the finished result.

Thursday 5 July 2012

Dismantling the Ensuite

One of the jobs I had this week was to de construct the Ensuite, we had to remove the fixtures, remove the the wall tiles and ceiling Coving and then the GiB and Villaboard, remove all the screws, nails and GiB glue.
Then I had to rip up the floor tiles.

Me chipping tiles
Wall tiles removed, now the mirror and GiB
Mirror removed
Where the toilet was
Starting on the Shower
Sam working on the shower
Starting on the floor
Shower walls stripped
And it's done